Back to National Assembly for Wales Homepage Subject Index  The Richard Commisssion
       
     
   
 
Welsh Assembly Government News * Members * Consultation * Calendar of events * Library of evidence * Frequently asked questions * External Links * Contact us
*
 

Written Response to the Richard Commission by Andrew Davies AM

Annex 2: Issue - To Seek Additional Powers Under the Electricity Act 1989

Contents

Annex 3

Introduction

1. The National Assembly for Wales is seeking to transfer powers currently held by the Secretary of State for Trade and Industry, under Sections 36 and 37 of the Electricity Act 1989.
 
Section 36 of the Act consents to the construction, extension and operation of a generating station over 50 megawatts (MW),
 
Section 37 consents to the installation of above ground electricity lines.
  The powers for maintenance and control of energy under the Energy Acts of 1976 and 1983 are not being sought and are fully reserved by the Department of Trade and Industry at UK level. These powers are not therefore devolved to the Scottish Executive.

Issue

2. At present responsibility for consenting power stations with a generating capacity of greater than 50 MW in England and Wales rests with the Secretary of State for Trade and Industry, under the provisions of Section 36 of the Electricity Act 1989. The Assembly Government is a formal consultee in the consents process but has no statutory role in the process. The Assembly Government’s has a limited role, while the Scottish Executive has the statutory powers to consent power stations under the Electricity Act 1989.
3. Power station projects are major infrastructure developments and as such there is a political and public imperative for the National Assembly for Wales to seek Section 36 and 37 functions under the Electricity Act 1989. In essence, such functions would allow the National Assembly for Wales to make its own decisions on all power generation developments within Wales and Welsh territorial waters and their associated overhead line provision (grid connection).

Current position

4. As matters stand, any proposed developments in Wales in excess of 50MW, and which are accompanied by an Environmental Impact Assessment, are made by developers to the Secretary of State, DTI. She undertakes a full consultation with statutory consultees, under the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999,which are the Local Planning Authority (LPA), Countryside Council for Wales and the Environment Agency and formal consultees, including the Welsh Assembly Government and Defence Estates.
5. In respect of the role of the LPA in the process, the procedure for obtaining consent under section 36 of the Electricity Act 1989 is set out in schedule 8 of the Act. Paragraph 2(i) of this schedule requires the applicant to serve notice on the Department of Trade and Industry (DTI) and to also inform the Local Planning Authority (LPA). The LPA then has 4 months to respond to the DTI. The LPA's role is therefore statutory and a formal part of the section 36 consent process. Although the LPA is not the decision-maker in relation to section 36 consent it will usually undertake its own wide consultations at the local level in coming to a decision on whether to support or object to the proposal.
6. If the LPA formally objects to the proposed development, a public local inquiry (Pli) must be held. Only the LPA's objection automatically triggers a Pli; in other cases an Inquiry will be held at the discretion of the Secretary of State for DTI.
7. The Welsh Assembly Government is a formal consultee in the Section 36 and 37 process for power stations of greater than 50 MW. As such it is asked to submit comment on the applications.
8. In formulating its comments, the Assembly Government is mindful of the limitations on what it can legally say in that Parliament has entrusted the consent decision to the Secretary of State for Trade and Industry alone. Because it is a decision which affects the rights of individuals (including those of the applicants and objectors) it is quasi judicial in nature and has to be taken in accordance with strict legal guidelines. Failure to do so would render the decision unlawful and liable to challenge.

Examples

9. Since devolution two power stations in excess of 50 MW have been proposed under the provisions of Sections 36 and 37 of the Electricity Act 1989. These are the Cefn Croes windfarm in Ceredigion and the Rassau Combined Cycle Gas Turbine power station in Blaenau Gwent.

The Cefn Croes Windfarm

10. The Cefn Croes windfarm sought consent for the installation of 39, 1.5MW wind turbine generators, the construction of access tracks and ancillary development on land which forms part of the Canolbarth Forest, Cefn Croes, Ceredigion. The Application was made under Section 36 of the Electricity Act 1989 to the Secretary of State for Trade and Industry. A separate application for a 132KV overhead line was also sought under Section 37 of the Electricity Act 1989.
11. In the case of Cefn Croes, Ceredigion County Council Development Control and Licensing Committee considered the application on 11July and found in favour of the Application. The County Council therefore resolved not to object to the proposal; this decision was taken against the recommendation of its officials.
12. As a formal consultee the DTI sought comments from the Welsh Assembly Government. In preparing a response to DTI and mindful of legal limitations, the Welsh Assembly Government took a strategic but objective approach in its consideration of the Cefn Croes application. It balanced views from across a broad range of its functions taking account of views given by statutory advisors like the Countryside Council for Wales and the Environment Agency. The Assembly Government's response fully set out the strategic views expressed from the economic, environmental, conservation, tourism, agriculture, planning and transport perspective.
13. The DTI Energy Minister announced the decision to approve the proposal on 23 May 2002.

Rassau

14. In 2001 the power generating company Enron, made an application under the provisions of the Electricity Act 1989 for the construction of a 1,200MW power station at Rassau near Ebbw Vale, the first such application since devolution.
15. The Local Planning Authority (LPA) was consulted as a statutory consultee by the DTI and the Assembly Government was a formal consultee. The LPA formally objected to the application; this would have automatically triggered a Pli but the company withdrew its application.
16. The project, had it gone ahead, would have contributed significantly to generation in SE Wales where electricity costs are around 7% above the UK average because of a shortage of local generation. The Enron proposal represented a £400 million capital investment. Construction would have taken two and a half years involving 900 workers, 1,200 at the peak of activity. One hundred and fifty permanent jobs were expected to be created.
17. Despite the significance of the project to the Welsh economy, The Welsh Assembly Government was no more than a formal consultee on the proposal. Regardless of the withdrawal of the project the Welsh Assembly Government's position meant that it effectively had no meaningful role in considering a project of major economic significance.